How do you migrate or upgrade IBM Maximo 7.6 to MAS 9?

The short answer

A Maximo 7.6 to MAS 9 migration has five stages: discovery of customisations, integrations and data; platform preparation on Red Hat OpenShift; data clean-up and validation; migration and regression testing in a non-production environment; and a rehearsed cutover with user training. Customisations and data quality decide the timeline more than the number of assets.

Step 1. Discovery: know what you have

Every reliable migration plan starts with an honest inventory. Before anyone sizes servers or talks dates, list:

  • Java customisations, automation scripts, escalations and cron tasks
  • Integrations: what connects, in which direction, through which technology (MIF, ACE, files, APIs)
  • Reports (BIRT and others) and who still uses them
  • Data volumes and data quality: hierarchy depth, classifications, failure codes, history
  • Users and roles, which feed the AppPoints model

The output is a phased plan and a list of decisions: what to carry forward, what to rebuild with MAS configuration, and what to retire.

Step 2. Platform: prepare OpenShift and identity

MAS runs on Red Hat OpenShift. Decide early whether it will run in your data centre, in your cloud account, or as a managed service. Plan sizing, storage, backup, network and single sign-on with your IT and security teams. This is often the longest lead-time item, so start it in parallel with discovery.

Step 3. Data: clean it while you move it

A migration is the cheapest moment you will ever have to fix asset data. At a minimum, fix the asset and location hierarchy, apply classifications to critical assets, and rationalise the failure-code hierarchy. Clean problem, cause and remedy codes are what make reliability reports, and any AI, trustworthy. Our guide to cleaning failure-code data covers this step in detail.

Step 4. Migrate and test

Run the upgrade in a non-production environment first, ideally more than once:

  • Rehearse the database upgrade and time it, so the cutover window is based on evidence
  • Build a regression pack from real processes: create a work order, plan it, issue parts, close it with failure codes
  • Test every integration end to end, including failure and retry paths
  • Let key users run their own scenarios before sign-off

Step 5. Cut over and support

Agree a cutover runbook with go and no-go criteria and a rollback plan. Train users on what has changed, especially if you are introducing Maximo Mobile or new start centres. Plan for a period of heightened support after go-live, when small configuration fixes matter most.

Maximo to MAS migration checklist

AreaReady when
CustomisationsEach one has a decision: carry, rebuild or retire
IntegrationsEvery interface is tested end to end, including errors
DataHierarchy, classifications and failure codes meet agreed quality targets
PlatformOpenShift sized, backed up, monitored and connected to SSO
LicensingAppPoints modelled against real user roles
PeopleUsers trained; support rota in place for go-live
FAQ

Related questions

How long does a Maximo to MAS migration take?

It depends mainly on customisations, integrations and data quality. Discovery gives you a phased plan with a realistic timeline before any migration work starts.

Do we have to use OpenShift?

Yes. MAS runs on Red Hat OpenShift, whether you host it yourselves, run it in your cloud account or use a managed service.

Should we clean data before or during the migration?

During. Fixing hierarchies and failure codes as part of the migration is cheaper than doing it twice, and it is what makes reliability reporting and AI work afterwards.